How to Write a Construction Daily Report
What belongs in a daily report, how to write entries that hold up later, and the mistakes to avoid. With a checklist and an example.
What belongs in a daily report, how to write entries that hold up later, and the mistakes to avoid. With a checklist and an example.
Updated October 11, 2026
A daily report, also called a daily log or site diary, records what happened on the job site each day: who was there, what work was done, what the weather was like and what got in the way. Weeks later nobody remembers the details. With the report you can look them up and show them.
It is kept by whoever has the overview of the site: the superintendent, the foreman, the owner of a trade business or the homeowner. Whether you have to keep one, and in what form, depends on your contract.
| Field | Entry |
|---|---|
| Date | Monday, October 12, 2026, 7:00 a.m. to 4:30 p.m. |
| Weather | cloudy, 48 to 59 °F, no precipitation |
| Workforce | Hartman Tile: 2 people, 8 hours. Brooks Electric: 1 person, 6 hours. |
| Work performed | Second-floor bath: wall tile set, grouting started. Kitchen: outlets installed. |
| Deliveries | Interior doors delivered, one door slab damaged (photo). |
| Delays | Painting in the hall not possible, the drywall compound is not dry yet. |
| Instructions | Owner: move the hall outlet 12 inches to the left. |
In the site diary app TagFix, every day has one entry with exactly these fields. The weather can fill in automatically, one tap copies workforce and equipment from the day before, and a closed day can only be extended by addenda. You share the report for one day or a date range as a PDF.
This guide is general information, not legal advice.